21st century supply chains (SC21) > how do I implement SC21? > SC21 engagement process

print friendly page

SC21 engagement process

entry points: customer led / regionally led / in house

 

milestone 1 (M1): lead key customer agreed

this milestone tracks when the key customer working group establishes who is the key customer contact for a supplier. The lead key customer is responsible for co-ordinating the other key customers for that supplier

milestone 2 (M2): champions contacted

this milestone is to track:

  1. firstly each lead key customer has contacted and coordinated with the other customers placing business with the supplier(s) they are the nominated lead for
  2. secondly lead key customer should engage with the regional partner(s)

milestone 3 (M3): supplier contacted

this milestone tracks that contact has been made with the supplier and that he has agreed to participate in SC21. Or if not please inform SC21 project office as soon as possible

milestone (M4): supplier signed up SC21

tracks that nominated supplier CEO has formally signed up to SC21 via the SBAC

milestone 5 (M5): 1st SC21 workshop held

an initial workshop including all necessary stakeholders has taken place

milestone 6 (M6): baseline status documented

document produced by key customer/region/supplier that captures the "point of departure" at the start of implementation in order to measure improvements achieved. ( e.g. number of audits per annum, how many improvement plans in place at start v no of KC's, how many relationship measured - improvement plans in place etc)

milestone 7 (M7): improvement plan agreed

this milestone tracks that an integrated improvement plan has been established with agreed scope, objectives and milestones